Lake Street & Dewey Court Project- Start of construction – Monday, July 29
NO BOAT or PADDLE CRAFT LAUNCHING (boats can be launched at Mendota Park or Marshall Park) - End of construction – October 31
- Pier/dock to be installed – Spring 2025
The planned general construction sequence includes: - Install water main on Lake St., working east from Allen Blvd.
- Install replacement sanitary sewer across Allen Blvd.
- After safe water is verified in the new Lake St. main, connect temporary service to the east condo building.
- Install water main south from Century Ave., down Dewey Ct. and across easement area at Century Harbor to connect with Lake St.
- Install storm sewer at the east end of Lake St.
- Construct wall and other landscaping at the new lakeshore park.
- Install new concrete elements (sidewalks, replacement curb).
- Majority of fine grading for restoration.
- Pave road – currently planned for mid-October.
|
|
|
|