The planned general construction sequence includes:

  1. Install water main on Lake St., working east from Allen Blvd.
  2. Install replacement sanitary sewer across Allen Blvd.
  3. After safe water is verified in the new Lake St. main, connect temporary service to the east condo building.
  4. Install water main south from Century Ave., down Dewey Ct. and across easement area at Century Harbor to connect with Lake St.
  5. Install storm sewer at the east end of Lake St.
  6. Construct wall and other landscaping at the new lakeshore park.
  7. Install new concrete elements (sidewalks, replacement curb).
  8. Majority of fine grading for restoration.
  9. Pave road – currently planned for mid-October.
Dewey St Design
Share on Facebook
Share on Twitter
Share via Email

Copyright © 2024 City of Middleton. All Rights Reserved.
7426 Hubbard Ave, Middleton, WI 53562

Powered by
CivicSend - A product of CivicPlus